Come to the Extraordinary Parish Council meeting at 7.00pm on 25th July in the Memorial Hall to find out more (the full Agenda is listed separately)
Telent Gigaclear Work
Under the Connecting Devon and Somerset (CDS) broadband program, Telent have orders to connect circa 12,000 homes and businesses will benefit from access to a new ultrafast full fibre network built by Gigaclear direct to each property.
We are planning to shortly start a community build program of works within your Parish. We would like to provide the Parish representatives with the opportunity to review this build and provide any further detail you may require. We are also happy, as required to attend any of your Parish meeting to present the build plan and answer any quires you may have. If you would like to take up this offer please contact the telent Project Manager as detail below.
We are planning to carry out works in the following community imminently –
Bigbury-on-sea
Current planned start and finish dates for this complete community area are –
Start – 01/08/18
Finish – 22/10/18
Please find below the Traffic Management Plans for this community area. This overview plan shows the planned trench rout and the traffic management we will be using to complete. These dates for the Proposed Build are subject to change depending on progress rates and other commitment. However, these details are our current plans. For up to date detail build notices please refer to Roadworks.Org
The work will involve road closures and diversion but we are aiming to maintain access for all residents and attempting to minimise disruption.
All residents and businesses will be contacted directly by letter and visits to the property if we plan to directly impact on your access or street.
Our Build Representative are as follows –
Name – Wyn Morgan
Telephone Number – 07967783438
Project Manager are as follows –
Name – Jody Walker
Email – Jody.Walker@telent.com